PROJECT FACTS

Project encompassed the renovation of an existing, commercial space of approximately 9,000 sq. ft. The first floor was slab-on-grade over approximately 5,000 sq. ft. with an additional 2,000 sq. ft. of supported floor and a 2,000 sq. ft. basement. Renovation included:

  • Removal of interior bearing walls
  • Relocation of one existing steel column
  • New openings in exterior walls for doors and windows
  • Evaluation of existing floor for support of lightweight fill
  • Evaluation of roof for new RTUs
  • New retaining wall at new exterior stair
  • New architectural fascia at southeast corner
  • New interior stair

Location: Maplewood, MO

Project Construction Cost: $900,000
 
Completion: 2006

Construction:The existing structure had an original structure and a subsequent addition. The original construction included exterior load-bearing brick walls with a wood-frame floor and a roof supported on steel beams. Interior columns supported the floor beams. The addition had exterior load-bearing block and brick veneer. The roof of the addition was a steel structure with steel bar beams and joists supporting a wood deck. Interior steel columns were also present in the addition.